Architectural Drawings: Types, Drawing Sets and How to Read Them

Architectural drawings are the technical drawings that turn a design into something a builder can price, permit and construct. A full set covers plans, elevations, sections, details and schedules, and in the US it becomes part of the construction contract.

Topic
Drawings
Updated
Reading time
15 min
Studio
Morales Arch & Design
Printed set of architectural drawings spread on a site office table
In this article
  1. What are architectural drawings
  2. Main types of architectural drawings
  3. What a full drawing set contains
  4. How drawings develop through the design stages
  5. How to read architectural drawings
  6. Interior drawings
  7. Hand drawing, CAD and BIM
  8. Who prepares architectural drawings
  9. Common mistakes and how to check a set
  10. Frequently asked questions

What are architectural drawings

Architectural drawings are two-dimensional technical drawings that describe a building well enough for someone else to build it. They start as rough sketches while a design is still forming and end as dimensioned instructions for contractors and suppliers, then as a record of what was actually built. In practice they are the shared language between the person who designs a building and the people who put it up.

On site and in contracts you will hear several names for the same thing. Architectural construction drawings, working drawings, building plans and blueprints usually mean the same set of sheets. Views, plans and details also get used loosely; "drawings" is the safest umbrella word for all of it.

A good set answers the questions a builder would otherwise have to guess at:

  • dimensions and the scale each view is drawn at;
  • material specifications for walls, floors, roofs and finishes;
  • structural elements such as foundations, beams and columns;
  • electrical, plumbing and HVAC layouts.

The same sheets are used for many jobs: getting a building permit, collecting contractor bids, estimating cost, ordering materials, coordinating trades during construction and, later, running and maintaining the building.

In the US the drawings are part of the contract documents. The contractor is legally bound to build what they show. The drawings set the criteria the finished building has to meet (the owner's requirements and the applicable building code) rather than telling the contractor step by step how to build it. That is also why problems are cheapest to fix on paper: moving a wall in a drawing costs a revision, moving it on site costs demolition. Treat a drawing set as a risk-management tool, on a new house and on a remodel alike.

Main types of architectural drawings

Most sets are built from a handful of standard views. Plans, elevations and building sections are orthographic projections: each one looks straight at the building from one direction with perspective flattened, so measurements can be taken from the drawing. Within one set, plans, elevations and building sections are normally drawn at the same scale.

Site plan

The site plan is the zoomed-out picture of everything to be built on the lot. It shows the building footprint against property lines and setbacks, utilities, parking, landscaping and topography.

Floor plan

A floor plan is a horizontal slice through the building seen from above. In US practice the cut is taken about 4 ft 6 in above the finished floor, so it passes through windows and doors. A floor plan typically carries room names and dimensions, wall types and thicknesses, door swings and window positions, tags that link to door and window schedules, material tags and, if useful, a furniture layout.

Floor plan, elevation and section sheets pinned on a wall

Elevations

Elevations are vertical views of the exterior faces, seen straight on. Because few buildings are simple boxes, each direction gets its own elevation. They show facade materials and finish legends, height references, openings and trim, the roofline and parapet heights.

Building sections

A section is a vertical slice through the whole building. It shows what a plan and an elevation cannot: floor-to-floor heights, stair geometry, how the walls sit on the foundation, the roof profile and the build-up of the building envelope.

Wall sections and details

Wall sections zoom in on one part of the wall, from foundation to roof. Detail drawings zoom in further, at a large scale, on parts that the general drawings show only roughly. They carry the most information per square inch of paper. Typical details cover wall-to-slab connections, window and door jambs, waterproofing, roof edges and parapets, and millwork and joinery.

Schedules

Schedules are tables that summarize items repeated across the building, so the plans stay readable. The usual ones are door, window, finish, fixture and hardware schedules. A tag on the plan points to a row in the schedule with sizes, types and materials.

DrawingViewWhat you find on it
Site planFrom above, whole lotFootprint, setbacks, utilities, parking, landscaping, topography
Floor planHorizontal cut, about 4 ft 6 in above floorRoom layout and sizes, wall types, doors, windows, material tags
ElevationEach face, straight onFacade materials, heights, openings, trim, roofline
Building sectionVertical cut through buildingFloor-to-floor heights, stairs, foundation, roof, envelope
Wall sectionVertical cut through one wallWall build-up from footing to roof
DetailLarge-scale close-upJunctions, flashing, jambs, parapets, joinery
ScheduleTableDoors, windows, finishes, fixtures, hardware

What a full drawing set contains

A drawing set is a bundle of sheets, and its size grows with the project. A large project can take years to document, with owner approvals and peer reviews along the way. The sheets are grouped by specialty:

  • Site: the overall site plan and what goes where on the lot.
  • Civil: earthwork, grading and sewer connections.
  • Structural: foundations, framing, beams and columns.
  • Architectural: plans, elevations, sections, details and schedules described above.
  • MEP: mechanical, electrical and plumbing, where the project needs them.
  • Landscape: planting and hardscape, where needed.

The project type decides which groups appear. If existing planting stays untouched, landscape sheets may be left out. A house addition may need little civil work, while a commercial building on a new lot needs all of it. For non-residential projects the set usually runs deeper, which is the territory of commercial drafting.

Several kinds of drawings are produced outside the design team. Shop drawings come from fabricators and trades and show exactly how they will make their part. Component drawings, at large scales up to full size, show the dimensions, construction and tolerances of a supplier's unit. Installation drawings cover things like plant rooms, ventilation and underfloor heating, and assembly drawings use exploded views to show how parts fit together. General arrangement drawings, on the other hand, pull plans, sections and elevations together to show the overall composition of the building.

How drawings develop through the design stages

Drawings change character as a project moves forward. Early on they are loose and fast; by the end they are precise, coordinated and legally binding. In US practice the phases are usually named as follows.

Concept sketches

Concept drawings are often freehand. They explore ideas quickly and are not meant to be accurate or final. Perspective sketches belong here too: they show how the building will look in three dimensions and are used for presentation, not for building.

Schematic design

The concept becomes a layout: massing, basic floor plans and the general arrangement of spaces. The client reviews these and gives feedback.

Concept sketches next to a stack of construction document sheets

Design development

Plans, elevations and sections are refined, materials are selected and the design is checked against codes. A 100% design development set is often used as a pricing set to get an early cost picture.

Construction documents

This is the longest phase. On larger projects the team issues checkpoint sets at 50%, 75%, 95% and 100% completion. The construction documents, together with specifications and schedules, form the production information contractors and suppliers build from.

Permit, bid and construction sets

The permit set (architectural, structural, MEP, site and landscape sheets plus supporting documents) goes to the authority having jurisdiction, usually the city or county building department. The bid set, often the 100% construction documents, goes to contractors for prices and lets them order the right materials. Once approved, the For Construction set is the final issue and becomes the single source of truth for every crew and trade on site.

As-built and record drawings

Buildings rarely go up exactly as drawn. During construction the contractor marks changes in red on the final construction issue. From those markups come the as-built or record drawings, which show what was actually built and are what an owner needs for future maintenance or remodeling.

StageTypical drawingsUsed for
ConceptFreehand sketches, perspectivesExploring ideas, presenting to the client
Schematic designMassing, basic plansAgreeing the layout
Design developmentRefined plans, elevations, sections, materialsCode check, early pricing
Construction documentsFull set at 50/75/95/100%Production information
Permit setAll disciplines plus documentsApproval by the building department
Bid setUsually 100% CDContractor prices
For ConstructionFinal issued setBuilding on site
As-builtRed-lined set, record drawingsRecord of what was built

How to read architectural drawings

Drawings use a standardized system of lines, symbols and notes so that a builder in another city reads the designer's intent the same way the designer meant it. Outlets, light fixtures and door and window types each have a symbol. Annotations and dimensions remove the guesswork about wall lengths, ceiling heights and materials. Once you know where to look, a set reads in a predictable order.

  1. Check the scale on every view. One sheet can mix scales, for example a plan at one scale and several details at a larger one. Never measure a view without reading its scale first.
  2. Read the legend. Symbols vary from project to project, so the legend on that set is the one that counts.
  3. Follow the callouts. Detail and section bubbles on a plan point to the sheet and view number where that part is drawn larger.
  4. Cross-reference tags with schedules. A door or window tag on the plan leads to its row in the schedule with size and type.
  5. Look for revisions. Revision triangles and dates show what has changed since the previous issue. Make sure you are working from the latest one.

The difference between the three main views is the direction of the cut. A plan is a horizontal cut seen from above. An elevation is the outside face seen straight on, with no cut at all. A section is a vertical cut that opens the building up like a sliced cake. Wall sections and details are simply closer views of the same idea, each adding more information about less of the building.

Interior drawings

Interior drawings take the same views inside the building. Elevations are usually drawn for the exterior, but they are also made for interior walls where a lot happens on one surface: a kitchen run, a bathroom vanity wall, built-in shelving or a reception counter. An interior elevation shows the wall straight on with cabinetry, openings, finishes and heights.

Floor plans for interiors often carry the optional furniture layout and material tags that a construction plan leaves out. Finish and fixture schedules list what goes on each floor, wall and ceiling and which fittings are installed where. Millwork and joinery details show how cabinets, panels and built-ins are made and fixed, at a large scale.

On a renovation, these sheets are what the cabinetmaker, tiler and electrician work from, so they deserve the same care as the structural drawings. If you are planning a kitchen, see how this fits into the wider process of kitchen design.

Hand drawing, CAD and BIM

For most of history architectural drawings were made by hand with T-squares, compasses and pencils. Every change meant erasing, and a bigger change often meant redrawing the whole sheet.

CAD tools arrived in the late 20th century and brought speed and precision. Copying, editing and reissuing drawings became easy, and fewer human errors crept in. CAD is still a good fit for 2D work and small renovations, and its files can be read almost anywhere. Its weakness is that each sheet is a separate drawing: change a window on the plan and you must update the elevation, the section and the schedule by hand, which is where coordination errors come from.

BIM, with tools such as Revit, builds a data-rich virtual model of the building and generates plans, elevations and sections from it. Change the model and every view stays consistent. Teams can also find clashes before work starts on site, such as a pipe running through a beam. That makes BIM the stronger option for coordinating larger projects. By one industry estimate, about 68% of architecture firms use BIM daily. If you want to go deeper, there are separate guides on architectural 3D modeling and on choosing a drafting program.

MethodStrengthsLimits
Hand drawingFast for freehand concept sketchesChanges mean redrawing sheets
CADPrecise 2D, easy revisions, readable everywhere, fine for small jobsEach sheet updated by hand, coordination errors
BIMOne model, consistent views, clash detection, suits larger projectsPays off most where many trades must be coordinated

Who prepares architectural drawings

Drawings are produced by architects, engineers, contractors and suppliers, and parts of the work are often outsourced to specialist firms. On a typical project the architect shapes the overall design and makes the key decisions about layout, form and materials. The architectural drafter turns that design into precise technical drawings. Good drafting needs more than software skills: the drafter has to know building codes and how buildings are actually put together, or the drawings will not survive plan review or the site.

Engineers prepare the structural, civil and MEP sheets. Trades and suppliers prepare shop, installation and assembly drawings for their own work, and the contractor produces the red-lined markups that become as-built drawings. Many owners and small practices hand the production side to outside architectural drafting services while keeping the design decisions in-house.

Common mistakes and how to check a set

Most problems on site trace back to a drawing that was unclear, out of date or out of step with another sheet. A short check before a set goes out for permit or bid catches many of them:

  • Every view states its scale, and details drawn at a different scale are clearly marked.
  • The legend matches the symbols actually used in the set.
  • Every callout bubble points to a sheet and view that exist.
  • Door, window, finish and fixture tags on the plans all have matching rows in the schedules.
  • A change on the plan has been carried through to elevations, sections and schedules (the usual CAD weak spot).
  • Structural, MEP and architectural sheets agree: no pipe through a beam, no duct where a column stands.
  • Revision triangles and dates are present, and the cover sheet lists the latest issue of every sheet.
  • The permit set includes all required disciplines and supporting documents for that building department.

The point of all this checking is cost. A conflict found on paper costs a revision; the same conflict found after the concrete is poured costs far more. A complete, coordinated set also gives contractors what they need for an accurate bid instead of a padded one.

Frequently asked questions

What are architectural drawings?

They are technical 2D drawings that describe a building's layout, dimensions, materials and systems precisely enough for it to be permitted, priced and built. They range from concept sketches to construction documents and as-built records.

What types of architectural drawings are there?

The core types are site plans, floor plans, elevations, building sections, wall sections, details and schedules. Around them sit structural, civil, MEP and landscape sheets, plus shop, installation and assembly drawings from trades and suppliers.

What is the difference between a plan, an elevation and a section?

A plan is a horizontal cut seen from above, in the US taken about 4 ft 6 in above the floor. An elevation shows an outside face straight on. A section is a vertical cut through the building that shows heights, stairs, foundation and roof build-up.

What is in a full drawing set?

Sheets grouped by discipline: site, civil, structural, architectural, and where needed MEP and landscape. The architectural part contains plans, elevations, sections, details and schedules for doors, windows, finishes, fixtures and hardware.

Who draws architectural drawings?

The architect sets the design and an architectural drafter produces the technical sheets. Engineers draw their own disciplines, and trades and suppliers prepare shop and installation drawings.

Should drawings be made in CAD or BIM?

CAD works well for 2D drawings and small renovations. BIM keeps all views consistent from one model and catches clashes, which makes it a better fit for coordinating larger projects.

What is an as-built drawing?

It is a drawing that records what was actually built. The contractor marks changes in red on the final construction set during the work, and these markups are turned into record drawings.

Are architectural drawings part of the contract?

In the US they are part of the contract documents, and the contractor is legally bound to build what they show. They define the required result rather than the construction method.

How do I read the scale and symbols?

Read the scale under each view, since one sheet can mix scales. Use the legend for that project's symbols, follow callout bubbles to detail sheets and check revision triangles and dates to be sure you have the latest issue.

Planning a build, a renovation or a new interior?

Send a floor plan, photos or a short description. We will reply with what drawings you need and how the work can be organised remotely.

Discuss your project

Read next

Commercial Drafting: What Goes Into a Commercial Drawing SetWhat commercial drafting covers in the US: design phases, sheets in the set, permit requirements, NCS numbering, specifications and a check before issue.Kitchen Design: A Practical Guide to Designing the KitchenKitchen design from brief to build: layouts, work triangle, aisle and counter dimensions, storage, ventilation, lighting, styles and remodel order.Architectural 3D Modeling: Process, LOD and SoftwareHow architectural 3D modeling works, from massing to BIM and drawings, what LOD 100 to 500 mean, and which software fits, with 2025-2026 US prices.