Interior Fit Out: What It Includes, How It Runs and What It Costs

An interior fit out is the construction work that turns the empty inside of an existing building into a space a tenant can actually use: walls, ceilings, floors, power, HVAC, plumbing, lighting, fixtures and furniture. The exterior walls, roof and structure are already there, so the job is about planning and finishing the interior to code and to the occupier's needs.

Topic
Fit-out
Updated
Reading time
12 min
Studio
Morales Arch & Design
Office floor mid fit-out with new metal stud partitions and exposed ductwork
In this article
  1. What is an interior fit out
  2. Interior fit out vs interior design vs renovation
  3. Shell types, tenant improvements and Cat A / Cat B
  4. What an interior fit out includes
  5. The interior fit out process step by step
  6. How much does an interior fit out cost
  7. Tenant improvement allowance and who pays
  8. How long a fit out takes
  9. Common interior fit out mistakes
  10. Interior fit out FAQ

What is an interior fit out

An interior fit out is the work done inside an existing building shell to make a space ready for occupation. The structure, roof and exterior walls are already built. What is missing is everything a business needs to function: partitions, ceilings, floor finishes, electrical distribution, HVAC, plumbing, lighting, fixtures and, at the end, furniture and equipment. In the US the same work is usually called an interior build-out or tenant improvement.

This is different from ground-up construction. A new building starts from bare land. A fit out starts with the cake already baked and deals only with what happens inside it. Fit out normally begins once core construction and the base architectural work are complete.

Empty commercial shell with bare concrete floor and exposed roof structure

In the UK, the developer usually completes the base building and the occupier, typically a tenant, carries out the final fit out. Approved Document L describes fit out as the work needed to complete the internal layout and servicing of a building shell for an incoming occupier.

A well planned fit out improves workflow, staff satisfaction and the way customers see the business. It can also make the space more energy efficient, which lowers bills and can lift property value. A poorly planned one leads to awkward layouts, code violations and paid rework. Tenants rarely run it alone: architects, engineers, contractors and project managers turn the brief into a code-compliant space.

Interior fit out vs interior design vs renovation

Interior design is the concept and planning stage: mood boards, sketches, layouts, colors, furniture and lighting selection. Fit out is the implementation. The designer decides how the space should look and work, and the fit-out team builds it, installs the systems and gets it ready for occupancy. If you want a closer look at the design side, see what an interior designer does.

The focus is also different. Design is about aesthetics and user experience. Fit out is about function and the infrastructure needed to occupy the space. Fit-out design works from the functional needs first, then the services those needs call for, with architects and engineers integrating mechanical, electrical and plumbing systems into the layout.

Timing differs too. Design can take weeks or months of concept work, planning and sourcing. Fit out is time-sensitive, because contractors, suppliers and trades must be coordinated on site in sequence.

A build-out is not the same as a renovation. A build-out takes an unfinished or partly finished space for a first or new tenant and adds new partitions, MEP systems and finishes. A renovation updates a space that is already finished and in use.

Shell types, tenant improvements and Cat A / Cat B

How much work a fit out involves depends heavily on the condition of the space you lease. US and UK markets describe this differently.

US terms

  • Cold dark shell. Exterior walls, roof and a concrete floor. No HVAC, no electrical distribution, no plumbing, no partitions. The most work and the highest cost.
  • Vanilla shell (warm shell). Basic HVAC, restrooms, electrical service and sometimes a ceiling grid. The tenant adds partitions, flooring, lighting and finishes.
  • Second-generation space. Previously occupied, so walls, plumbing and even kitchen equipment may be reused. Putting a restaurant into a former restaurant costs far less than starting from a shell.
  • Tenant improvements (TI). Customizations made for a specific tenant, usually negotiated in the lease, often with a landlord allowance toward the cost.

UK terms

  • Shell and core. Structure, cladding, base plant and finished common areas: reception, lobbies, stairs, toilets, lifts, basement and parking.
  • Cat A. A functional but empty floor, usually completed by the landlord to market the space: raised floor, suspended ceiling, basic lighting, air conditioning and fire systems. No rooms, kitchen or furniture. A typical Cat A floor uses 60 x 60 cm raised panels over a 10-25 cm void for power and data. Cat A is not the same as a Grade A building.
  • Cat A+. A landlord-built plug-and-play office with generic meeting rooms, a tea point and often furniture. Tenants can move in within 4-8 weeks.
  • Cat B. Built on top of Cat A to the tenant's requirements: bespoke layout, meeting rooms, furniture, branding and technology. Usually commissioned by the tenant.
  • Turnkey. The developer hands over a space fully fitted and ready to use.

A simple way to picture it: Cat A is like an unfurnished rental, Cat B is like a furnished house. None of these categories has a standard legal definition, so the lease must spell out what is included.

What an interior fit out includes

Scope varies with the shell and the use, but a full commercial fit out typically covers the following:

  • Space planning, design and construction drawings (more on this in fit out drawings)
  • Demolition of existing walls, ceilings or finishes
  • Framing and partitions, doors and glazed screens
  • Mechanical, electrical and plumbing (MEP), including power and data
  • HVAC distribution and controls
  • Flooring, ceilings and paint
  • Lighting
  • Fixtures and millwork: reception desks, kitchens, built-in storage
  • Life safety: sprinklers, fire alarms, exit signage
  • Furniture, fixtures and equipment (FF&E)

The use of the space shapes the priorities. In an office the fit out is about making the most of the floor: workstations, meeting rooms and communal areas, as covered in office fit out design. In healthcare, treatment rooms and waiting areas must meet medical standards. Restaurants carry the heaviest services load because of kitchen equipment and ventilation.

The interior fit out process step by step

  1. Define needs. Function, headcount or customer numbers, and the brand experience you want. For larger offices this often starts with workplace strategy and space planning.
  2. Space planning and design. Layouts and drawings that account for building code, accessibility and workflow.
  3. Permitting. The local building department reviews the drawings before work starts. This usually takes longer than expected, so build in a buffer.
  4. Bidding. General contractors price the finalized plans. Compare them on cost, relevant experience and timeline.
  5. Construction. Usually in this order: demolition, framing, MEP rough-in, then finishes.
  6. Inspections. The building department inspects at set stages, for example before walls are closed.
  7. Certificate of occupancy and move-in. After the final inspection, furniture, equipment and signage go in. Closeout includes a punch list of defects to fix and the final documentation.

There are two common delivery routes. In the traditional route, the tenant hires an architect, a contractor and suppliers separately. In design and build, one firm handles design and construction, which is increasingly popular because there is a single point of responsibility. Work can also be carried out in an occupied building if it is sequenced to limit disruption.

Permits are needed for almost every commercial interior build-out, covering electrical, plumbing, mechanical and structural work. Skipping them risks fines, rework and a delayed certificate of occupancy.

How much does an interior fit out cost

Most of a fit-out budget goes to construction and installation rather than design. US figures for 2026 per square foot look like this:

Space type (USA, 2026)Typical cost per sq ft
General office, standard finishes$50-$150, average about $65
Office with traditional private offices$193-$224
Retail, basic$40-$90
Retail, mid-range$90-$180
Retail, premium$150-$300
Medical office$150-$350
Restaurant$200-$480

Private-office layouts cost more because of extra framing, doors and individual rooms. Restaurants sit at the top because of the kitchen and ventilation; see restaurant fit out for that case.

Restaurant kitchen fit-out with ventilation hood ducts and stainless steel being installed

What pushes the price up

  • A cold dark shell costs 30-50% more to fit out than a vanilla shell for the same use.
  • High-end lighting, custom millwork and premium materials can roughly double the cost compared with standard commercial finishes.
  • Location: the West Coast runs about 11% and the Northeast about 7% above the national average.
  • A tight labor market in peak season can add 15-30% to installation costs.
  • Specialist equipment and technology, as in trading floors or medical suites.
  • Design revisions: many rounds of changes add to design fees.

In the UK, Cat A typically costs about £50-100 per sq ft and Cat B about £60-120 per sq ft. A London office fit-out runs from about £90 per sq ft at a basic level to £190 or more at high spec including furniture and AV. Mechanical and electrical work can make up about 60% of a UK fit-out cost and may qualify for capital allowances, which is worth raising in lease negotiations.

Cat A has a lower cost per sq ft but still needs furnishing later. Cat B costs more upfront but needs little further investment beyond maintenance. Many spaces go through Cat A and then Cat B. Cat A+ costs the tenant less on day one, but the landlord recovers it through rent, so the total over 5-10 years can end up similar. The real difference is cash flow.

Tenant improvement allowance and who pays

Who pays for the fit out depends on the lease. In the US, the landlord often contributes a tenant improvement allowance and the tenant pays anything above it. The national average TI allowance is about $43 per sq ft in 2026, while Class A space in gateway cities can carry three to four times that.

Use (USA, 2026)Typical TI allowance per sq ft
Office$10-$100
Retail$10-$250
Restaurant$100+

In major office markets, allowances are about 66.7% higher than before the pandemic, and longer lease terms unlock bigger ones. Still, a TI allowance is not free money. Compare the total occupancy cost over the life of the lease: base rent, free-rent months and escalations.

In the UK, a tenant with complex needs sometimes contributes to the Cat A cost so that work is not built and then ripped out. Instead of a cash contribution, the landlord may offer a rent-free period as a notional fit-out contribution, starting from practical completion of the shell and core.

How long a fit out takes

A US commercial build-out typically takes 6-20 weeks from permitting to move-in. A cold dark shell sits at the long end, a second-generation space at the short end. Permitting is the step most often underestimated.

In the UK, going from Cat A to Cat B usually takes 16-24 weeks of design and construction, plus lead time for furniture and equipment. A Cat A+ space lets a tenant move in within 4-8 weeks.

Interior design work before the fit out can take weeks or months of its own. Finalizing the design before construction starts gives more predictable costs and fewer surprises on site.

Common interior fit out mistakes

  • Underestimating the shell condition. A $40 per sq ft allowance on a cold dark shell can leave the tenant paying $50-$90 per sq ft out of pocket.
  • No contingency. Keep 5-15% of the budget in reserve.
  • Negotiating TI and shell condition separately. They affect each other and belong in the same conversation with the landlord.
  • Rushing design. A change on paper is cheap. The same change after construction starts costs far more.
  • Vague category definitions. Because Cat A and Cat B have no standard definition, the contract or agreement to lease must state exactly what is done and by whom.
  • Ignoring base building limits. Cat A quality varies. Ceiling height, floor loading, power and cooling capacity limit what a Cat B fit out can achieve.
  • Forgetting the exit. A bespoke Cat B fit out is usually stripped out at lease end under dilapidations. Agree reinstatement terms in the lease before moving in.

When choosing between categories, Cat A suits tenants who manage design in-house, already own furniture or plan to sublet. Cat B suits those who want a ready-to-use space with tailored meeting rooms and technology. A bespoke Cat B is justified when generic space simply does not work: trading floors need extra power and cooling, law firms need acoustic privacy, creative agencies want open floors. Over a 10-15 year lease, the cost is spread out. The decision comes down to budget, timeline and how much design control you want.

Interior fit out FAQ

What is the difference between a build-out and a renovation?

A build-out prepares an unfinished or partly finished space for a first or new tenant with new partitions, MEP systems and finishes. A renovation updates a space that is already finished.

How long does an interior fit out take?

In the US, typically 6-20 weeks from permitting to move-in, longer for a cold dark shell. In the UK, Cat B from Cat A takes 16-24 weeks plus furniture lead time.

Who pays for the fit out?

It depends on the lease. The landlord may provide a tenant improvement allowance or a rent-free period, and the tenant covers the rest.

Do I need a permit for an interior fit out?

Almost all commercial interior build-outs need permits for electrical, plumbing, mechanical or structural work. Without them you risk fines, rework and a delayed certificate of occupancy.

What is a vanilla shell?

A space with basic HVAC, restrooms, electrical service and sometimes a ceiling grid. The tenant adds partitions, flooring, lighting and finishes.

How much does a fit out cost per square foot?

In the US in 2026, general office space averages about $65 per sq ft within a $50-$150 range, retail runs $40-$300, medical office $150-$350 and restaurants $200-$480.

Is Cat A the same as a Grade A building?

No. Cat A describes the level of fit-out in a tenant's space. Grade A describes the quality of the building itself.

Planning a build, a renovation or a new interior?

Send a floor plan, photos or a short description. We will reply with what drawings you need and how the work can be organised remotely.

Discuss your project

Read next

What does an interior designer do: duties, process and costWhat an interior designer does: space planning, materials, lighting, drawings, budget and site work, how a project runs, how it differs from decorating.Fit Out Drawings and What a Complete Set IncludesWhat fit out drawings contain, from plans and ceilings to details and schedules, how permit, shop and as-built sets differ, and a pre-issue checklist.Office Fit Out Design: From Empty Shell to Working OfficeOffice fit out design explained: Cat A and Cat B scope, space planning, acoustics, light, 2026 cost per square foot, timeline and how to choose a team.