Permit drawings: what goes into a building permit drawing set
Permit drawings are the set of scaled sheets you submit to the city or county so a plans examiner can check your project against the building code before any work starts. A house or duplex needs only a handful of sheets, while a commercial set runs from a dozen to more than a hundred, in a fixed order and drawn to set scales.
- Topic
- Permit drawings
- Updated
- Reading time
- 16 min
- Studio
- Morales Arch & Design

In this article
- What permit drawings are and why the city asks for them
- What a building permit drawing set includes
- Cover sheet and code analysis
- Site plan: the sheet that fails most often
- Floor plans, sections and elevations
- Structural, MEP, life safety and accessibility sheets
- Drawings for building permit: sheet counts, scales and stamps
- Why permit drawings get rejected and how to speed up review
- Who can prepare permit drawings
- Permit drawings FAQ
What permit drawings are and why the city asks for them
Permit drawings are the construction documents a building department reviews before it issues a permit. In the US the requirement comes from IBC Section 107.2, which asks for construction documents "of sufficient clarity" to show that the work will meet the code. Jurisdictions read that line as a fairly standard list of sheet categories, so a commercial permit set usually contains 8 to 12 types of sheets submitted in a set order.
The point of review is a second check. The plans examiner looks over the design of the architect, the engineer and the trades against the local code before anything gets built. That is why a nice-looking presentation plan rarely passes on its own: the examiner wants dimensions, code references, notes and schedules they can verify line by line.

No construction can start until the permit is issued. In cities such as San Diego, permits are needed for new buildings, additions, remodels and electrical, mechanical or plumbing work, and applications go in online. The city also runs separate permits for demolition, fire systems (sprinklers and alarms), grading and noise. Partial demolition is usually covered by the building permit, not a separate demolition permit.
Codes and ordinances differ from one jurisdiction to the next, even between neighboring towns in the same metro area. Before drawing anything, find out which city or county reviews your address and which code editions it has adopted.
What a building permit drawing set includes
A full building permit package bundles architectural, structural, mechanical, electrical and plumbing drawings and goes to the city or county as one submission. On commercial jobs the sheets are grouped into lettered series, each owned by a discipline.
| Series | What it covers | Usually prepared by |
|---|---|---|
| G (general) | Cover sheet, project data, code analysis, sheet index, deferred submittals | Architect |
| C (civil) | Site plan, grading, drainage, utilities | Civil engineer |
| A (architectural) | Floor plans, elevations, sections, details | Architect |
| S (structural) | Foundation, framing, connections, special inspections | Structural engineer of record |
| M, E, P | Mechanical, electrical and plumbing equipment, distribution, schedules | MEP engineers |
| LS (life safety) | Occupant load, egress, fire-rated assemblies | Architect |
| AD (accessibility) | ADA and ANSI A117.1 clearances | Architect |
| T (energy) | Envelope, mechanical and lighting compliance calculations | Architect or engineer |
The architect of record normally draws the G, A, LS and AD series and coordinates the other consultants. For a house or duplex the set is much shorter. Portland, Oregon, for example, expects a typical residential set to have a site plan, floor plans, elevations, cross sections and detail drawings, plus a foundation plan for a new building or addition.
Some items travel with the drawings rather than as sheets. Sacramento lists energy compliance documents when conditioned floor area grows, truss calculations when trusses are used (and they must match the roof and floor framing), and product listing numbers from approved testing agencies such as UL, ICC or IAPMO for roofing, skylights, spas and fireplaces. When a remodel or tenant improvement moves walls or ceilings, it may also need plans for the automatic fire extinguishing system.
Cover sheet and code analysis
The cover sheet is the first thing intake staff read, and a missing block on it can stop the package before plan review even starts. A complete commercial cover sheet carries six blocks:
- project data: address, APN, legal description, owner, applicant, and the licensed designer with stamp;
- code analysis;
- sheet index with revision dates;
- list of deferred submittals;
- general notes;
- vicinity map and north arrow.
The code analysis names every code by edition year, for example 2021 IBC, 2020 NEC, 2021 IMC, IPC, IFC and IECC, the 2010 ADA Standards and ANSI A117.1-2017. It states the occupancy classification, how mixed uses are separated, the construction type (I through V, A or B) and sprinkler status (NFPA 13, 13R, 13D or none).
Allowable area and height are shown as calculated numbers under IBC Section 506 and Tables 504.3 and 504.4, not just as a pass or fail. Occupant load totals follow Table 1004.5, and required separations follow Section 508.
Deferred submittals under IBC 107.3.4.1, such as items a specialty contractor will design later, must be listed here by name. Rules on them vary: Sacramento does not allow deferred submittals for residential projects at all, and on commercial work they must appear on the cover sheet.
Site plan: the sheet that fails most often
The site plan gets sent back more often than any other sheet, because its requirements come from zoning and the local authority rather than from the IBC. Portland calls it the most important document in a residential set, since every review group has to sign off on it. A complete site plan means fewer requests for missing information later.
On a commercial job the site plan shows:
- property lines with bearings and distances that match the survey;
- setbacks dimensioned to the nearest building face;
- existing and proposed footprints;
- easements with their recording references;
- FAR and site coverage compared with the zoning maximums;
- accessible parking under 2010 ADA Section 208;
- grade contours and drainage arrows;
- fire department access, hydrant and FDC location under IFC 503.
For a house, Sacramento asks for two versions, existing and proposed, unless one drawing shows both clearly. It should include every structure on the lot down to sheds, setbacks, drainage direction, landscaping, sidewalks and the adjoining streets and alleys. Portland wants the whole lot shown at a scale of at least 1" = 10'.
Easements for sewer, power or service lines cannot be built on, and an HOA or planned community can add its own approval before the city will look at the plans. In much of the US, stormwater rules may call for a separate stamped civil set.
Floor plans, sections and elevations
Floor plans get the closest reading of any sheet. On commercial work the minimum scale is 1/8" = 1'-0", and dimension strings run from overall, to bay, to openings. Room names must match the occupancy on the cover sheet. Doors and windows carry tags such as D-01 and W-01 tied to schedules, rated wall assemblies are hatched by wall type, and plumbing fixtures are dimensioned to centerline.
Egress has to be shown against the travel distance limits of IBC Table 1017.2 and the common path limits of Table 1006.2.1. Accessible clearances need actual dimensions, because when a clearance is not dimensioned, reviewers assume it does not comply.

What a residential floor plan shows
For houses, Portland asks for a floor plan of every level where work happens, plus a roof plan, with existing and proposed work told apart and a north arrow on each. Its floor plans show full and partial height walls, room sizes and uses, window location, size and type, bearing walls and beams, stairs and smoke detectors. Plumbing fixtures and electrical outlets can sit on the floor plan or on separate plans. Sacramento adds door and window operation type, lights, fireplaces and cabinets.
A new building or addition also needs a foundation plan with slabs, footings, rebar, concrete strength, crawl space access and vents. Below-grade work has its own points, covered in our guide to basement drawings for permit.
Sections
A section is a slice through the building from roof to ground. It shows footing size and depth, foundation wall height, joists, studs and rafters, insulation, finishes, ceiling heights and eaves, including gutters. Portland accepts one typical section for a simple project. Full sections go at 1/4" = 1' or larger, wall sections and details at 1/2" = 1' or larger. Any project with stairs needs stair details with materials, support and dimensions.
Elevations
Elevations are needed for any change to the outside of the building. They show the ground line and slope at the walls, windows, doors, siding, roofing and guardrails.
Structural, MEP, life safety and accessibility sheets
Structural
Structural permit drawings have two parts. The plans show layout, openings, roof framing, foundation, beam and column sizes and connection details. The specifications set out lumber grades, concrete and rebar, fasteners, sheathing and anchors. A full structural set includes foundation and framing plans, sections, schedules and general notes with design loads (dead, live, snow, wind, seismic), soil bearing values and the special inspections required by IBC 1704.
Details are referenced between sheets, for example a footing detail called out from the foundation plan. In Sacramento the structural plans must be signed and stamped by the engineer of record, while stamped calculations are needed only when the project falls outside the conventional framing provisions of the California Building Code.
The architect should check that the engineer cites the same code edition as the cover sheet; a mismatch draws an automatic correction. Holdowns and shear walls also must not clash with window and door openings on the architectural plans.
Mechanical, electrical and plumbing
MEP sheets carry equipment plans with schedules, electrical panel schedules with loads calculated per NEC Article 220, a one-line diagram for services over 400 amps, and a plumbing fixture count under IBC Table 2902.1. PE stamps are required above thresholds set by each state. If the systems side is new to you, see what MEP works means in practice.
Life safety
For Use Groups A, B, E, F, H, I, M, R-1, R-2 and R-4, and for commercial tenant improvements, life safety is its own sheet rather than a markup on the floor plan. It shows the occupant load of each room, travel distance, common path, dead-end corridors under Section 1020.5, rated assemblies, exit signs, emergency lighting and fire extinguishers under IFC 906. Fire barriers (707), fire partitions (708), smoke barriers (709) and smoke partitions (710) are different wall types with different rules. The fire marshal often reviews only this sheet.
Accessibility
The accessibility sheet has an accessible route plan and toilet rooms drawn at 1/4" scale or larger, with the 60" turning circle, the 60" x 56" clear space at the water closet and grab bars at 33" to 36" high under 2010 ADA 609.4. It also covers door maneuvering clearances (ADA 404), parking signs mounted at least 60" to the bottom of the sign and slopes no steeper than 1:48. Where the ADA and ANSI A117.1 differ, the stricter one applies.
Drawings for building permit: sheet counts, scales and stamps
How many sheets you need depends on the size and type of project. Typical counts for commercial work:
| Project | Typical sheet count |
|---|---|
| Small tenant improvement under 5,000 sf | 12 to 18 sheets |
| New building, 5,000 to 50,000 sf | 30 to 60 sheets |
| Large project | More than 100 sheets |
A set that is far heavier than the job, such as 200 sheets for a 4,000 sf tenant improvement, reads as over-documented and slows review. A house or duplex usually needs only the site plan, floor and roof plans, foundation plan, a section or two, elevations and details.
Common scales
| Drawing | Commercial (typical) | Residential, Portland |
|---|---|---|
| Site plan | Per local authority | 1" = 10' or larger, whole lot |
| Floor plans | 1/8" = 1'-0" minimum | 1/4" = 1' |
| Enlarged plans, toilet rooms | 1/4" = 1'-0" | n/a |
| Full sections | Varies by project | 1/4" = 1' minimum |
| Wall sections | About 3/4" = 1'-0" | 1/2" = 1' minimum |
| Details | 1-1/2" = 1'-0" or larger | 1/2" = 1' minimum |
Who stamps which sheets
On commercial work the architect stamps the G, A, LS and AD sheets, the structural engineer stamps the S sheets, and MEP engineers stamp their sheets where the project exceeds the state thresholds. Licensing law is set by each state, so check yours before deciding who signs what.
Sample drawings for building permit
The quickest way to see a passing set is to look at one. Many city and county websites, including Los Angeles, San Francisco and Seattle, publish approved sample permit sets for single-family homes, ADUs and simple tenant improvements. Use them to see the expected level of detail in your jurisdiction, not as plans to copy onto your lot.
Why permit drawings get rejected and how to speed up review
Most corrections come from a small group of repeat problems:
- an incomplete cover sheet, which can stop the package at intake;
- a deferred submittal that appears in a consultant's sheets but is missing from the cover sheet list;
- a site plan that leaves out zoning data, setbacks or easements;
- accessible clearances drawn but not dimensioned;
- the structural engineer citing a different code edition than the cover sheet;
- MEP equipment shown on a plan with no schedule entry, or a schedule entry with no location on the plan;
- shear walls or holdowns that clash with openings.
The fix for the MEP problem is to cross-reference every piece of equipment by tag. For the rest, a careful check of the cover sheet against each discipline's sheets before submittal catches most of it.
Drafting conventions examiners expect
Sheet numbers follow the US National CAD Standard: A-101 for the first floor plan, A-201 for elevations, A-301 for sections, A-501 for details. Every sheet carries a title block with sheet number and title, project name, date, revision, stamp, scale and key plan. Keep the north arrow consistent, and if plan north is more than 15 degrees off true north, show both. Revisions are marked with clouds and delta tags, dated, and summarized on the cover sheet.
Residential departments have their own format rules. Portland asks for black ink only, no color and no photos, text at 12 point for dimensions and notes, no tracing-paper originals, and high-resolution scans. Lines must be straight, measurements precise and everything to scale. Anything that needs explaining should be written on the drawings themselves, and utility locations should be checked against the real service connections before they are drawn.
Who can prepare permit drawings
For commercial buildings, the architect of record leads the set and licensed engineers prepare and stamp the structural and MEP parts. For houses the rules are looser in some places. Portland lets anyone draw residential plans, provided they are to scale, with straight lines and precise measurements. Structural sheets still need an engineer's stamp where the jurisdiction asks for one, as Sacramento does.
Stock plans bought online often lack the lot-specific detail a reviewer needs, and some jurisdictions refuse plans that were not prepared by a professional licensed in that state. If you are weighing whether to hire, our article on whether you need an architect walks through the usual cases, and how much an architect costs covers fees.
A few steps save time whatever route you take. Look up old records first: in Portland, drawings for work done after 1976 may already be on file. Book one of the free 15-minute appointments with a plans examiner that some cities offer. Check the city's permit timeline page so you know what to expect.
Submission format varies too. Portland needs one set when you apply online, or four sets when dropping off in person, and one comes back stamped as the jobsite copy. Once plans are approved, do not mark up that set. Changes during construction go on a new set that the plans examiner and planner review again, and San Diego, for example, requires city approval of changes before the work is done, with a separate application for construction changes and deferred submittals.
Permit drawings FAQ
Where can I find sample drawings for a building permit?
Many city and county websites, such as Los Angeles, San Francisco and Seattle, post approved sample permit sets for single-family houses, ADUs and simple tenant improvements. Start with your own building department's site, since local requirements differ.
How many sheets does a permit set need?
A small commercial tenant improvement under 5,000 sf usually runs 12 to 18 sheets, a new building of 5,000 to 50,000 sf runs 30 to 60, and large projects pass 100. A house typically needs a site plan, floor and roof plans, a foundation plan, sections, elevations and details.
Do permit drawings need a stamp?
On commercial projects the architect stamps the general, architectural, life safety and accessibility sheets, the structural engineer stamps the structural sheets and MEP engineers stamp theirs above state thresholds. For houses, some cities let owners draw their own plans, but structural plans may still need an engineer's stamp. Check your state licensing law and local rules.
What scale should permit drawings be?
Commercial floor plans are drawn at 1/8" = 1'-0" or larger, enlarged plans at 1/4", wall sections at about 3/4" and details at 1-1/2" or larger. Portland asks for residential floor plans and sections at 1/4" = 1' and a site plan of at least 1" = 10'.
What is the most common reason permit drawings are rejected?
The site plan fails review more than any other sheet, because it has to meet zoning and local requirements. Incomplete cover sheets, missing deferred submittals, undimensioned accessible clearances and mismatched code editions between disciplines are other frequent causes.
Can I change the drawings after the permit is approved?
Yes, but the changes need approval before the work is built. Do not mark up the approved set; prepare a revised set for the plans examiner and planner to review again.