Design fit out: what it covers, how it runs and what it costs
Design fit out is the planning, installation and construction work that turns a bare shell or white box into a space people can occupy. A 10,000 sq ft office takes roughly 10-12 weeks to fit out, and the 2026 North American benchmark sits near USD 297 per sq ft. What you pay and how long you wait depend on what the landlord leaves behind and how early the brief is fixed.
- Topic
- Fit-out
- Updated
- Reading time
- 10 min
- Studio
- Morales Arch & Design

In this article
- What a design fit out covers
- Fit out design vs interior design and renovation
- Shell and core, Cat A, Cat A+ and Cat B
- The fit out design brief and site survey
- The fit out design process step by step
- Who does what, and which delivery route to choose
- Fit out design cost per square foot
- How long a design fit out takes
- Keeping fit out design on scope and budget
- Design fit out FAQ
What a design fit out covers
A fit out starts where the base building stops. The structure exists, the interior is empty or close to it, and the work adds whatever a tenant needs before opening the doors: ceilings, floors, partitions, plumbing, HVAC, wiring, data cabling and an internet connection. The agreed scope sets out which existing elements stay, which are altered and which are installed new.
In the United States the same job is usually called a build-out or tenant improvements. Whichever word appears in the lease or the proposal, tie it to a written scope, because the label alone commits nobody to anything.
A full fit out design normally deals with six groups of work:
| Group | Typical content |
|---|---|
| Layout | Room arrangement and partitions |
| Finishes | Floors, ceilings, joinery |
| Building services | Lighting, power, ventilation, plumbing, fire systems |
| Furniture | Workstations, seating and loose pieces |
| Technology | Cabling, AV, access control, room booking |
| Support areas | Kitchen, reception, signage |
The landlord provides some of these and the tenant the rest. A responsibility schedule that names who designs, supplies, installs and tests each item settles the boundary before anyone prices it.
Done well, the result uses the floor area efficiently and shows the brand to visitors and staff alike. Ergonomic furniture, clear circulation and current technology support satisfaction and productivity, while sustainable materials and smart building systems improve how efficiently the space runs.
Fit out design vs interior design and renovation
Interior design is the concept and planning phase: mood boards, sketches, layouts, palette, furniture, decor. Interior fit out is the implementation that follows, with construction, installation and coordination of trades, usually after the core construction and architectural work is finished. The emphasis shifts too. Interior design leans toward appearance, and fit out toward function and the infrastructure required for occupancy.
That is why fit out design works backward from use. It begins with what the space has to do, derives the services needed to support that, then coordinates both with architects and engineers.
Cost behaves differently as well. A fit out price is easier to predict because the design is frozen before work begins. Interior design fees climb with every revision round and with custom finishes.
Renovation changes a space that is already in use. It can be minor (paint, fixtures), moderate (flooring, cabinetry) or major (structure, layout). Because a fit out begins on a blank floor, it often finishes sooner than a renovation that involves structural work. UK figures from 2023 put fit out at GBP 40-95 or more per sq ft and a light cosmetic renovation at GBP 10-30.
Shell and core, Cat A, Cat A+ and Cat B
The starting condition decides how much is left to design. The category names come from UK leasing practice and turn up in leases and proposals well beyond it.
| Category | What is in place | What remains |
|---|---|---|
| Shell and core | The structure | Lighting, power, heating and some interior walls. Suits large occupiers building from the ground up |
| Cat A | Basic services: lighting, heating and cooling, electrics, plumbing, ceilings, raised floors | Everything specific to the occupier. The usual state of rentable space |
| Cat A+ | Landlord has already fitted and furnished the space | Little, since the aim is a quick move-in |
| Cat B | Space completed to the occupier's specification | Nothing major: partitions, furniture, light fixtures, window treatments, wall coverings and branding are part of the package |
Read the actual specification before trusting a category name, since one landlord's Cat A may leave out items another includes. A turnkey contract can cover the Cat B scope with one party carrying defined responsibility for it.
The fit out design brief and site survey
Three questions open the brief. What does the organization need now, what will it need over the lease term, and what kind of culture or atmosphere should the place support? Answer them through a space analysis, ideally before the lease is signed, while the choice of premises is still open.
Then put numbers in. Record headcount, expected growth across the lease and how often people attend. Hybrid work changes the arithmetic. Hybrid portfolios now run at about 56 desks per 100 staff, against roughly 80 in 2022, and the freed floor area goes to focus rooms and team zones.
Sector matters. A trading floor, a studio, a reception and a back office each have their own acoustic, technology and layout requirements. A weak brief comes back later as design changes, delays and overruns.
Survey the building before committing to a layout:
- mechanical and electrical services and their condition
- available power capacity
- raised floors and ceilings
- structural limits
A test-fit, meaning the brief drawn onto the real floor plate, shows whether the premises work. From there the office layout design can move into detail.
The fit out design process step by step
- Discovery and brief. Users, activities, occupancy data, audience and first mood boards.
- Premises assessment and concept. Survey, test-fit, space planning and a concept the client approves.
- Detailed design. Colors, materials and lighting are chosen, engineers add their input, and the fit out drawings are developed for pricing and construction.
- Procurement and approvals. Contractor appointment, permits and legal paperwork with local authorities, orders for long-lead items.
- Construction. Structural work, electrical, plumbing and HVAC.
- Furnishing. Furniture and fixtures go in on dates agreed with the build program. Renderings help confirm the selection.
- Testing and occupation. Quality checks, systems testing and handover.

These steps rarely run in a neat line. Design, cost planning, procurement and approvals overlap, and how far depends on the delivery route. Permits can take time, so start the paperwork while details are still being resolved. Small choices at the build stage often have a large effect, which is a good reason to settle furniture and layout early.
Who does what, and which delivery route to choose
Interior designers lead the concept and the design; their wider role is explained in what an interior designer does. Engineers confirm that the proposal is safe. The fit out contractor acts as the single point of contact during the works and coordinates designers, architects, subcontractors and the client.
On the traditional route the architect or designer completes the design and a contractor builds it. The client may need a designer, builder, space planner and furniture supplier, possibly joined by a surveyor, structural engineer and project manager.
Design and build puts all of that under one turnkey party. In the UK, up to 85% of fit outs under GBP 1 million go this way. Contractors offering it claim it is 30-40% faster, a figure drawn from their own projects rather than independent comparison. A related model, design-build-furnish, adds furniture to the same contract so that its delivery is planned with construction dates.
Fit out design cost per square foot
Average 2026 office fit out costs by region:
| Region, 2026 | USD per m² | USD per sq ft |
|---|---|---|
| North America | 3,200 | about 297 |
| EMEA | 2,300 | about 214 |
| Latin America | 1,800 | about 167 |
| Asia Pacific | 1,550 | about 144 |
| Global average | 2,150 | about 200 |
The UK breakdown for 2026 shows how the total splits. It assumes a base build with Cat A power and HVAC in good order.
| GBP per sq ft, UK 2026 | Low | Mid | High |
|---|---|---|---|
| Construction | 70 | 90 | 120 |
| Furniture | 20 | 35 | 60 |
| AV and IT | 5 | 10 | 15 |
| Dilapidations | 15 | 18 | 20 |
| Security | 1 | 2 | 3 |
| Total | 111 | 155 | 218 |

London Cat B projects in 2026 can come in lower: GBP 45-95 per sq ft for construction plus GBP 12-35 for furniture, with a quality specification starting around GBP 65 for the build and GBP 800-900 of furniture per person. The gap comes from scope and specification, so compare inclusions before rates.
The main cost drivers are cosmetic versus structural change, AV and communications, furniture level (sit-stand desks, task lighting, acoustic panels), floor area, deadline and procurement route. A complete budget lists:
- construction, furniture and technology
- professional and approval fees
- relocation
- dilapidations, the cost of reinstating space under a lease
- contingency and taxes
For a first pass on your own floor area, a building cost estimator helps structure the numbers before quotes arrive.
How long a design fit out takes
A typical 10,000 sq ft office in the UK takes 10-12 weeks (2026). Compressing that means out-of-hours work and a higher price. A quoted duration may cover construction only, so ask what is inside it.
Counted from the first concept meeting, the job is longer. Concept and design run for several weeks, construction for a few months to a year, and finishing for anything from a few weeks to a few months. End to end, the process runs from six months to two years, with the upper end reserved for large and complicated projects.
Plan backward from the move-in date. Allow time for approvals, long-lead furniture and joinery, site restrictions and systems testing. Where the premises stay in use, add time for limiting disruption to daily operations.
Keeping fit out design on scope and budget
Most overruns begin before construction, in a thin brief or an unclear boundary between landlord and tenant work. These habits reduce the risk:
- Make decisions about furniture and layout early, since both affect budget and schedule.
- Reconcile exclusions and owner-supplied items before comparing tenders. The lowest figure may simply contain less.
- Check whether existing furniture and partitions can be reused.
- Assess risks at the start and hold a contingency in both money and time.
- Hold regular progress meetings and track actions in project-management software.
- Put permits and legal paperwork from local authorities into the program as tasks with dates.
A fit out has to meet the safety regulations that apply at its location. Requirements vary, so confirm them with the local authority and the engineers on the project before the design is frozen.
Design fit out FAQ
What is the difference between fit out and renovation?
A fit out prepares an empty shell for occupation. A renovation updates an existing space, from repainting and new furniture up to structural and layout changes.
Is fit out the same as interior design?
No. Interior design produces the concept, layouts and material choices. Fit out carries them out through construction, installation and coordination, with the focus on function.
What affects fit out cost most?
Structural versus cosmetic scope, AV and IT, furniture specification, size, deadline and procurement route. The condition of the base building matters too, as most rates assume working Cat A services.
How much should I budget for furniture?
In the UK in 2026, furniture runs about GBP 20-60 per sq ft, while London Cat B projects can come in at GBP 12-35. A quality specification comes to roughly GBP 800-900 per person.
Are dilapidations included in a fit out price?
They are a separate item, although they belong in the overall budget. Allow GBP 15-20 per sq ft in the UK in 2026.
Does design and build change the cost?
The procurement route is one of the factors behind the price. Design and build gathers several appointments into one contract, so compare its inclusions with the separate fees on the traditional route.
How long does an office fit out take?
About 10-12 weeks for 10,000 sq ft as a typical UK case. Add the time for brief, design, approvals and long-lead orders if the quote covers construction only.